You have a great project plan, with lots of detail.  It’s properly documented and you have built a schedule that gets everything done by the date that the project sponsor wants.

However, now the team have started working on the project, it is clear that they are sticking to their own timescales and not paying any attention to your masterpiece.

In fact, at the last team meeting they went as far as to tell you that your schedule is completely unrealistic.

OK, you missed out the testing phase, but surely that won’t take very long?  Everyone is doing what they can, and the team is working long hours to get tasks completed on time, but they are starting to resent the fact that you signed them up to this.  You don’t know how long you can keep the project going when it’s obvious that the team doesn’t believe in the plan or the schedule.

Sound familiar?

You may have seen this in your own project or you may have participated in a project team where you don’t have faith in the schedule. Here are some warning signs to look out for in this situation:

  • Your project team complain about the timescales.
  • Tasks are not being completed on time, if at all.
  • Tasks are being completed that are not on the plan.
  • You are putting your team under pressure to complete tasks by the milestone dates.
  • Everyone is working long hours.
  • The team’s morale is falling, along with their confidence in you.

The risk of ignoring the warning signs

The project will run late

If you notice these warning signs on your project and do nothing, the project will get later and later. Tasks will not be delivered on time. The project sponsor will become more disillusioned with your ability to deliver on the promise of your schedule. In turn, you may put more and more pressure on your team to speed up. The risk here is that you will collectively cut corners and end up delivering a low quality product that is not fit for purpose. Your customers won’t be pleased about that.

Morale will suffer

Morale in the team, and their willingness to work with you, will fall. Eventually you might find that they won’t work on your projects at all, and you’ll gain a reputation for being a slave driver whose projects always run late.

What should you do?

You can’t plan in a vacuum.  At the end of the day, it’s not you who will be doing all the tasks – that’s what the members of the project team will do. While you have an important part to play in helping them achieve their tasks, they will be the ones sitting at their computers coding, or mixing the cement to build the bridge, or delivering the training course. Involve them in working out what needs to be done to meet the project objectives and how long it will all take.

If your plan and schedule are unrealistic, start from scratch and build new ones, with the involvement of all the right people.  In summary, you need:

  • A complete list of tasks required to deliver the project.
  • Accurate timescales for these.

What should I do?

Get the key members of your team altogether to work out a new, realistic plan and schedule that they can all buy into. Acknowledge that your current working plan is no good and that you need to set a new baseline against which to track progress. Essentially, you are starting to plan this project from scratch, and you need their help.

Document all the tasks

As a group, review all the work breakdown structures and plans you have so far. The person doing a job will have a better understanding of what it actually involves than you ever will. So let them tell you what is required to get the task done. What is missing from the original plan? How does the task break down into sub-tasks? If you can, delegate the creation of sub-plans to the workstream leaders. Help them to use iMindQ or a similar tool to ensure everything is captured.

The aim here is to get a comprehensive list of what needs to be done to achieve the project’s objectives. Rely on your experts to help you develop this list – it will help them feel more accountable for the deliverables, and more comfortable with the overall plan.

Understand the dependencies

Once you know what needs to be done, it is time to start putting the tasks in order to create the schedule. Dependency management is important here. Again, rely on the experts in your team to help you build the dependencies into the schedule. Take into account:

  • What order do the tasks need to be completed in?
  • What tasks can be run in parallel?
  • What can be started early?
  • Who needs someone else to have finished before they can start?
  • What needs to finish at the same time as something else?

Once you understand the order of tasks and their dependencies you can start putting in some dates.

Create the schedule

The team didn’t think much of the original schedule you created, so this time ask them for their input.  They have probably spent more time carrying out this type of work, and unless it is a unique project or they are very new to their job they are likely to have done it before.  Given all their experience, they should be able to come up with some realistic estimates for timeframes for all the tasks on the plan.

There is no harm in challenging some of the dates – you don’t want the team to be able to pull the wool over your eyes.  As the project manager you should find a balance between making up the milestone dates yourself and allowing the team to define their own dates so far in the future that they all get to work half days and the project takes ages to complete.  Work together to create stretching but achievable target delivery dates.  And put some contingency time explicitly in the schedule if you are worried that there is a degree of uncertainty in the estimates.

Finally, it’s time to present your new schedule to your sponsor.  It is highly likely that the result of doing this exercise is a project that will finish later than you originally had in mind.  It’s difficult to tell your project sponsor that your initial estimates were wrong.  However, what you now have is a project plan that you can believe in, deliver to and that is backed by all the members of your team.  That’s the message to give your sponsor.

Aim for collaborative planning - always

You are not the expert when it comes to carrying out the work for each of these tasks – so draw on the expertise in the team and involve team members when producing a plan and schedule.  You will get better buy in from the team as a result, and everyone will have more confidence that the project will deliver on time. You know you’re in a good place when:

  • You have a comprehensive list of tasks for the project.
  • You understand the dependencies between tasks.
  • You have worked with your team to set realistic estimates for the duration of these tasks.
  • You have built a credible schedule with input from your team.