Earned Value Reporting – Estimate to Completion
Posted by Brad EgelandIn this article on Earned Value Reporting we’ll look Estimate to Completion. As explained in the book “The Project Management Question and Answer Book” by Newell and Grashina, the Estimate to Completion describes the expected cost needed to complete all the remaining work for a schedule activity, work breakdown structure component, or the project.
Newell and Grashina’s book is the basis for much of the information in this discussion on Estimate to Completion.
What is the estimate to completion?
The estimate to completion or the ETC is an estimate of the additional money that will be necessary to complete the project. It is calculated from the estimate at completion that we discussed previously.
The estimate to complete is something that can and should be derived as quickly and as early in the process and/or life cycle of the project as possible because it will help the team budget accordingly. However, if the estimate is done early and there is a need at some point to modify it, this can be done once or – if needed -even more than once during the life cycle of the specific project in question.
Can you get into trouble with estimates at completion? You bet you can. As we have seen in the discussion of the EAC, there are many ways that this estimate can be made. The most common form is the budget at completion divided by the cost performance index. This is only a rough estimate of what the project will cost when it is completed.
Using the estimate at completion predicts that the project will overrun or underrun its budget at the end of the project. While it is a good thing to keep the stakeholders and the managers of your company informed that projects are in trouble, it is a weak support for asking that the project be given additional budget. A good project manager who wants to keep his job will take the EAC and use it as additional supporting information to show that the project budget was originally overor understated. In addition to the EAC, the project manager should have much supporting information as to why the project is in the condition that it is in.
Earned Value Reporting – To Complete Schedule Performance Index
Posted by Brad EgelandIn this article on Earned Value Reporting we’ll look at something similar to the To Complete Cost Performance Index – the To Complete Schedule Performance Index, or TCSPI. The To Complete Schedule Performance Index tells us the required schedule performance index that will be needed to meet the schedule.
The book “The Project Management Question and Answer Book” by Michael Newell and Marina Grashina is the source for much of this overview.
What is the to complete schedule performance index?
The to complete schedule performance index, or TCSPI, is similar to the TCCPI except that it calculates a required schedule performance index that will be necessary to meet the project schedule. This measure is rarely used. It is included here for completeness. It has the same problems as the TCCPI and is even more abstract and difficult for people to understand.
The calculation for the TCSPI is done by dividing the work remaining by the remaining schedule.
TCSPI = (BAC – BCWP) / (BAC – BCWS)
It can be seen that as a project’s schedule performance index moves below one, the TCSPI will increase and become greater than one. Although called an “index”, this is not really accurate since all indexes indicate something bad when they fall below one and this index indicates something bad when it is greater than one.
There is a mathematical difficulty with this term as well. If a project is over budget toward the end, it is possible for the BAC and the BCWS to be equal. This produces a division by zero and a point of discontinuity.
Under normal conditions it results in a value that indicates the required performance that the project must have from now until the end of the project.
Example:
Suppose a project is somewhere near 50 percent complete:
BCWS = $100,000
BCWP = $95,000
ACWP = $97,000
BAC = $200,000
SV = BCWP – BCWS
SV = -$5,000
What is the TCSPI?
TCSPI = (BAC – BCWP) / (BAC – BCWS)
TCSPI = (200,000 – 95,000) / (200,000 – 100,000)
TCSPI = 1.05
Notice that if the schedule variance remains the same as the end of the project approaches, the TCSPI increases rapidly. Suppose we have the following when the project is approximately 95 percent complete:
BCWS = $195,000
BCWP = $190,000
ACWP = $192,000
BAC = $200,000
SV = BCWP – BCWS
SV = -$5,000
What is the TCSPI?
TCSPI = (BAC – BCWP) / (BAC – BCWS)
TCSPI = (200,000 – 190,000) / (200,000 – 195,000)
TCSPI = 2.00
As we approach the end of the project, the schedule variance has not changed, but the TCSPI has changed from 1.05 to 2.00. This means that the work that must be accomplished from now to the end of the project must take place at a rate that is twice as fast as was originally planned.
Earned Value Reporting – To Complete Cost Performance Index
Posted by Brad EgelandIn this article on Earned Value Reporting we’ll examine the To Complete Cost Performance Index. In a nutshell, the To Complete Cost Performance Index tells us the cost performance that is required to complete a given project for it’s original budget based on how it is performing right now.
The book “The Project Management Question and Answer Book” by Michael Newell and Marina Grashina is the source for much of this overview.
What is the to complete cost performance index?
The to complete cost performance index, TCCPI, tells us the required cost performance that is necessary to complete the project for the original budget based on the performance of the project as of today.
The to complete cost performance index is a seldom-used indicator, and there are some difficulties in its use. The TCCPI is calculated by dividing the work remaining by the money remaining in the budget to do it. The remaining work in a project is simply the difference between the work already accomplished, the BCWP, and the total work of the project, the BAC. You will recall that when the project is completed, the BCWP must exactly equal the BAC. Mathematically it is impossible for this not to happen since the BAC is equal to the sum of the BCWP and is also equal to the sum of the BCWS. The remaining budget for the project is simply the difference between the total budget for the project, again the BAC, and the amount of money that has been spent to date, the ACWP.
TCCPI = (BAC – BCWP) / (BAC – ACWP)
It can be seen that as a project’s cost performance index moves below one, the TCCPI will increase and become greater than 1. Although called an “index”, this is not really accurate since all indexes indicate something bad when they fall below one and this index indicates something bad when it is greater than one.
The TCCPI gives us a rough estimate of the performance that is required for the remaining portion of the project in order for the project to be completed for the original budget. A TCCPI of 1.33 indicates that the project team must perform with a CPI of 1.33 from now until the project is completed in order for the project to be completed at the original budget.
There is a mathematical difficulty with this term as well. If a project is over budget toward the end of the project, it is possible for the BAC and the ACWP to be equal. This produces a division by zero and a point of discontinuity.
Under normal conditions it results in a value that indicates the required performance that the project must have from now until the end of the project.
Example:
Suppose a project is somewhere near 50 percent complete:
BCWS = $100,000
BCWP = $95,000
ACWP = $97,000
BAC = $200,000
CV = BCWP – ACWP
CV = -$2,000
What is the TCCPI?
TCCPI = (BAC – BCWP) / (BAC – ACWP)
TCCPI = (200,000 – 95,000) / (200,000 – 97,000)
TCCPI = 1.02
In this example the project would be required to do all of the remaining work at a 2 percent higher cost performance than was originally planned. This may be particularly difficult since the cost performance index to date is only 98 percent. We will be asking the project team to improve their cost performance by some 4 percent.
Notice that if the cost variance remains the same as the end of the project approaches, the TCCPI increases rapidly. Suppose we have the following when the project is approximately 95 percent complete:
BCWS = $195,000
BCWP = $190,000
ACWP = $192,000
BAC = $200,000
CV = BCWP – ACWP
CV = -$2,000
What is the TCCPI?
TCCPI = (BAC – BCWP) / (BAC – ACWP)
TCCPI = (200,000 – 190,000) / (200,000 – 192,000)
TCCPI = 1..25
As we approach the end of the project, the cost variance has not changed, but the TCCPI has changed from 1.02 to 1.25. This is an indicator that the cost variance will be much more difficult to recover now than it was earlier in the project.
Earned Value Reporting – Estimate at Completion
Posted by Brad EgelandIn this article on Earned Value Reporting we’ll closely look at the concept of Estimate at Completion. What the Estimate at Completion tries to tell us is the forecast value of the project when the project has been completed.
Much of the following was derived from the book “The Project Management Question and Answer Book” by Michael Newell and Marina Grashina.
What is the estimate at completion?
The estimate at completion, frequently shown as the EAC, is the forecast value of the project when the project is complete. It should be noted that the EAC can be calculated in a number of different ways and is only an indicator of what the project’s cost will be at the end of the project.
The estimate at completion is a value that can get project managers in trouble. In its most commonly used form it is the budget at completion divided by the cost performance index.
EAC = BAC / CPI or EAC = (BAC x ACWP) / BCWP
This is a rather pessimistic estimate of the amount of money that will be spent at project completion. It says that the things that have gone wrong in the project until now will continue to go wrong, and we will not learn how to improve them between now and the end of the project. There are many reasons why this is true. There could be bias in our estimates. If the early items in the project were underestimated, it is likely that the later items in the project will be underestimated as well. If there is a chronic problem that has been evident in the early part of the project and the same people and equipment will be used on the later project activities, then the EAC will probably be accurate by this method. On the other hand, if different estimators and team members or different pieces of equipment are being used later in the project, the EAC may not indicate the project’s true estimated cost at the end.
Unfortunately, as we will see, much of the research that has been done in this area indicates that projects that are over budget when they are 25 percent complete are very likely to finish over budget. Not only that, but these projects are likely to finish with a worse cost performance index than they had when they were 25 percent complete.
Earned Value Reporting – Schedule Performance Index
Posted by Brad EgelandIn this article on Earned Value Reporting we’ll look at the Schedule Performance Index. The Schedule Performance Index refers to how the project is performing in terms of actually following the project schedule.
Much of the following information came from Newell and Grashina’s book entitled “The Project Management Question and Answer Book.”
What is the schedule performance index?
The schedule performance index is a measure of how well the project is doing in terms of following the project schedule. It is a comparison of the project tasks that were planned to be accomplished to the work that was really accomplished. The index is a value that allows projects of different sizes to be compared.
The schedule performance index is like the schedule variance discussed previously with one important difference. When we calculated the schedule variance, the result was a figure in dollars. If the dollars were negative, the variance was considered bad, and if the dollars were positive, the variance was considered good. The problem with this method is that it is difficult to compare projects of different size to one another. It would be better to have a measure that gives the health of the project regardless of its size. For this purpose we will use indexes.
Instead of subtracting the budgeted cost of work scheduled from the budgeted cost of work performed, as we did when we calculated the schedule variance, we will divide the same two numbers.
SPI = BCWP / BCWS
SPI = EV / PV
We can see that if the project is following its plan, the amount of work accomplished and the amount of money spent to accomplish it are the same, and the resulting value will be one. So, an index of one means that the project is following its plan.
If the budgeted cost of work scheduled is greater than what is being accomplished, the denominator in the fraction will be larger than the numerator, and the resulting value will be less than one. This is a bad condition. If the budgeted cost of work scheduled is less than what is being accomplished, the resulting number will be greater than one and this is considered good.
Example:
A project is two weeks behind schedule at the time of the calculation. The project has fifteen people working full-time. Assume that each person costs $1,000 per week. BCWS at this point in the project is $500,000. What is the schedule performance index?
The project is two weeks behind schedule and there are fifteen people working full-time on the project. This results in being behind schedule by thirty person-weeks or $30,000.
SPI = BCWP / BCWS
The BCWP is $500,000 ? $30,000 = $470,000.
The BCWS is $500,000.
SV = BCWP – BCWS = -$30,000
SPI = BCWP / BCWS = $470,000 / $500,000 = 0.940
Notice that a smaller project such as one that had a BCWS of $50,000 and a BCWP of $47,000 would also have a schedule performance index of 0.940. Again, this helps the project manager who is managing different parts of a project in which the sizes of the parts are different. The schedule performance index, like the cost performance index, indicates the health of the project regardless of its size.