Earned Value Reporting – Intro Part 2
Posted by Brad EgelandIn the previous Intro Part 1 article we began to look at Earned Value Reporting as described in Newell and Grashina’s book “The Project Management Question and Answer Book.” In this Intro Part 2 article, we’ll exam Cumulative Variance Reports before diving deepr into other EVR concepts and reporting mechanisms.
Cumulative Variance Reporting
Sometimes in very large projects there is a problem with representing the project plan and the other earned value factors on a cumulative basis. When the project budget is very large, the vertical scale of the report is so small that minor but important variations cannot be seen well. In this situation a variance reporting method can be used.
To plot the earned values on a variance chart as shown in Figure 2 we simply plot a horizontal line and label it zero. Now, instead of plotting the actual values of the BCWS, BCWP, and ACWP we plot the differences between the BCWS and the other two earned value reporting factors. When we do this, the vertical scale that we need is greatly reduced in size since we are concerned only with plotting the difference between the earned value factors and not the entire budget of the project.
FIGURE 2
The next one, the ACWP or AC, is pretty simple too. This stands for the actual cost of work performed. Like the BCWS it is a plot over time of expenditures. This time, instead of plotting the project’s planned expenditures we are plotting the project’s real expenditures over time. At the end of each reporting period, we take the total amount of money that was spent on the project during that period and plot it as an addition to the total amount of money that had been spent as of the last reporting period.
It is important that every expenditure that is made on the project be collected and be collected in a timely way. The timing of the collection of the actual cost of work performed must match the anticipated timing of the expenditures that were planned and plotted as the BCWS. This is terribly important since, if expenditures are collected early or late in the project in relation to the project plan, the earned value report will show a positive or negative variance when there may really be none.
The ACWP plot is a cumulative plot as well. If the project expenditures are actually what they were planned to be, then the ACWP and the BCWS lines will plot one on top of the other. If the lines do not coincide, there is something different from the plan taking place in the project. We are either spending too much or too fast or we are not spending enough or fast enough to meet our plan.
The next factor is the BCWP or EV. This is the only one that is a little tricky. BCWP stands for the budgeted cost of work performed. It is sometimes called the earned value as well. This is where we get the name of the earned value report. Like the BCWS and the ACWP, the BCWP is a plot of money over time. If you recall, we said earlier that each of the project tasks has a budget and schedule associated with it. The BCWP is a plot of the work that was actually accomplished. If we complete a task that had a budget of $1,000, then the BCWP for that task when it is completed is $1,000. We plot this on a cumulative basis as well. It does not matter whether we spend $1,000 or $2,000 or any other amount to accomplish this task, we earn and plot only the budgeted amount in the BCWP.
Like the ACWP, the BCWP should plot right on top of the BCWS line. If the plot of the BCWP is above or below the BCWS line, it means that the number of tasks that are being completed is greater than or less than the plan. This tells us that we are ahead of or behind schedule. If we have done all of the tasks that were supposed to be done at this point in time, the cumulative value of the BCWP will be precisely equal to the BCWS.
When we put all three of these plots together, we have the earned value report. The plots should plot right on top of one another if the project is being done on time and in accord with the budgeted amount that was in the project plan.
Example:
Suppose a project is in progress and as of today the planned expenditures for the project were to have been $500,000. Suppose also that there were five tasks and the tasks had budgets of $30,000, $100,000, $250,000, $100,000, and $20,000, respectively. The actual cost of each of the tasks that were worked on was $11,000, $120,000, $230,000, $105,000, and $20,000. Tasks 1, 2, 3, and 4 are complete.
What are the BCWS, ACWP, and BCWP (PV, AC, and EV)?
- BCWS is $500,000
- ACWP is $486,000
- BCWP is $480,000
From these figures we can see that the accomplishments of the project as of today are somewhat less than what was planned for. This is the difference between the earned value and the planned value to date. The planned value is the BCWS and the earned value is the BCWP. This means that we are $20,000 behind schedule.
We can also see that the actual cost is $14,000 less than the planned expenditures to date. This means that we are somewhat under budget. Unfortunately we are $14,000 under budget but also $20,000 behind schedule. If we add the $20,000 of work that should have been completed but was not, we find ourselves projecting a $6,000 over budget condition. It could be that things are actually worse than they appear at first glance. If the performance to date continues, the amount over budget will probably be even higher at the end of the project. This is usually considered a bad situation.