Dealing with Unreasonable Customer Expectations

Posted by Brad Egeland

We all hope that customer expectations have been accurately set coming out of the sales process.  Ideally, the customer will have a draft project schedule in hand, a budget (i.e., contract/price), Statement of Work (SOW), and hopefully their own list of business processes and high-level requirements that they’ve shared with sales to get to this point of the project – deal signed and complete and ready for Kickoff.

Often a customer will say “we need this project completed in ‘x’ number of weeks.”  You want to accommodate the customer as much as possible.  After all, they are the customer and they’re paying for it.  But it’s a dangerous trap to fall into when you agree to any sort of customer proposed timeline before you have a detailed understanding of the customer’s affected business processes, the requirements of the project and the resources for the project. 

The Crazy Promise

I led a project for a major airline that had been given the impression by our sales team that the implementation of an enterprise solution could be done within 90 days of Kickoff.  Never mind that the configurable/customizable system…

  • Had never been implemented for an airline industry customer
  • Usually took 6-12 months to implement in known industries
  • Was targeting UAT and deployment over major holidays when resources from both organizations were planning time off

The airline managed to coerce Sales into agreeing to basically ‘guarantee’ the 90-day implementation timeline.  Remember, this is without any involvement from Project Management – I would never have agreed to the 90-day timeline if I had a say in it.  The airline also put out a press release in the airline industry that they were implementing this enterprise-wide system in 90 days…no pressure!

The Project

A project that starts off with unreasonable expectations from the customer definitely does a disservice to the customer.  Not only can major problems be experienced, but also other issues like timeline crisis, major scope issues, requirements changes, and budget overruns are all highly likely occurrences on a project of this nature.

In my example project, we hit the 90-day mark while still only about 2/3 of the way complete.  The customer’s expectations had long since been reset, but because so much had been promised to the customer they were, needless to say, not happy during most of the engagement.  We added resources, went onsite for some rapid configuration work, and therefore began to run into the very predictable budget issues along with the timeline issues we were already experiencing.

Summary

For this project, in the end the outcome was a fully implemented and workable solution.  However, customer satisfaction began low and never really recovered.  The original deadline was missed by 3 full months.  The budget went $38,000 over and due to issues on the customer side, it was never successfully embraced and deployed in the organization and is still floundering in terms of usage and internal deployment to this day.

Customer satisfaction is everything and if your project starts out with unreasonable customer expectations, run!  Seriously though…work hard to bring reality in to focus.  Educate the customer; work with the customer to reset the project timeline expectations based on the known requirements.  Work with them to reset the budget expectations based on the known requirements. 

Also work with management in your own delivery organization to ensure that you have the proper expertise on your delivery team.  At this point you want to do your best to both meet the reset customer expectations and minimize customer dissatisfaction that has likely already started due to the original expectation issues.

Share this post:
  • LinkedIn
  • TwitThis
  • Facebook
  • del.icio.us
  • Digg
  • StumbleUpon
  • Sphinn
  • Mixx
  • Propeller
  • Technorati
  • Print this article!

Related posts:

  1. What the Customer is Trying to Tell You
  2. Project Managers’ Top Ten Challenges
  3. The Art of Negotiation – Part 1
  4. When Project Funding Hits the Wall
  5. Never Say No to the Customer

Tags: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

3 Comments to “Dealing with Unreasonable Customer Expectations”

  • The biggest problems in this kind of situations is not a disconnection between customer’s expectations and reality but a disconnection between what some representatives say (sales, senior management) and what company is able to do.

    This reminds me a situation when I went to a difficult project meeting with customer. I was expecting to discuss what our team of two developers can achieve in specified time span. I got a headshot when a project sponsor repeated me what our CEO told them before the deal was signed. They were told that if that would be needed more than a half of our 50 engineers can work on their project. I actually wished I’d had at least 5 people which I could spare to the project project. Anyway, there was nothing reasonable I could tell unless I wanted to admit they were lied and the project is doomed.

    When deal is already signed it’s usually too late to educate customer. Another good idea is to ignore the pressure, accept the fact there will be significant slip and try to do your best. If you try too hard to reach impossible-to-meet deadline you’ll lose more time and annoy the client more.

  • This is what change management for Agile methodology is all about. Trying to educate both customers and your sales force is a major challenge. That is why engineering really must be involved in what is usually called the “technical pre-sales” phase. Software engineering is fairly abstract, ergo hard to visualize. May I recommend using building construction metaphors when asked why one change is easy to implement while another is hard? Take a look at http://stackoverflow.com/questions/274054/what-are-your-favorite-metaphors-for-technical-concepts/274148#274148 as an example.

  • I fully agree with the statement “Customer satisfaction is everything”. Keeping the regular triangle- scope, budget, schedule- is not sufficient without the customer satisfaction.
    I suggest follow this rule- say ” Yes, but…” for unreasonable demands. Let the customer understand the consequence of his request – cost and time- and let him decide (as long it does not damage you or get you involved in something illegal).

    http://giladlsh.wordpress.com/2009/08/21/5project-steps/

    Gilad

Post comment

Spam protection by WP Captcha-Free